DC intervention at the CEA
Preparation tasks:
-
Check with QL if the missing QSFP cables were received- the cables have been delivered and are staged in the rack
- Prepare the ansible configuration for the new C06 server as far as possible as we don't known the disk ids yet
- Look at the procedure to configure the switchs (LACP for the active ones / Bootstrapping for the new ones / Spanning tree / VLAN configuration / ...)
- ?
List of task to perform on the 2 scheduled days:
-
Check the current installation compared to what is declared in the inventory (server positions, wiring, ...) -
Upgrade bifur/bofur to latest compatible OS10 release -
Update the access switchs (bifur/bofur) configuration to use active/active LACP -
Install and configure the admin network of the C06 switchs -
Add the C06 switchs in the active network -
Check and finalize the C06 hardware installation -
Configure the ports of the C06 servers -
Install and configure the new OSDs in C06 -
Move dwalin003 to the C06 rack and reconfigure switch ports
Documents:
- DELL switchs documentation: https://mybox.inria.fr/smart-link/719c127c-3c0a-4759-a054-8d4d26da6052/
- HP switchs configuration: https://mybox.inria.fr/smart-link/359869e2-04fd-4ca2-ba24-63801557384c/
- Infra IPs plan: https://mybox.inria.fr/smart-link/ee444dae-a042-4572-81b3-97fe9a354664/